MIDILLI HYDROELECTRIC PLANT

Scope of the Work: Midilli Hydroelectric Plant
Project Technical Specifications
Installed Capacity: 3 x 34,24 MWm =102,72 MWm
Average Production: 416,00 GWh/year
Project Flow Rate: 105,00 m3/sc
Transmission Channel Characteristics
Trapeze Channel Type: 2 090,00 metres
Vertical Channel Type: 16 465,30 metres
Tunnel: 5 043,70 metres
Tunnel Characteristics
Tunnel Type: Circular, with Free Surface
Tunnel Diameter: 6,00 metres
Total Tunnel Length: 5 043,70 metres
Net Head: 106,24 metres
Penstock Pipe Diameter: 3 x 3 000 mm
Regulator Type: 6 x Radial Gate, Concrete Weighted Power House
Hydraulic Turbines: 3 x Vertical Axis Francis
Power House Generators: 3 x Vertical Axis Synchronous
Agreement Date: 30/04/2008

Midilli Hydroelectric Plant

Agreement Date: 30/04/2008 - Work Completion Date: 31/08/2010

 