YAVUZ HYDROELECTRIC POWER PLANT
Project Technical Specifications
Installed Power: 3 x 7,50 MWm =22,50 MWm
Average Production:82,00 GWh / year
Project Flow Rate:106,70 m3/sc
Transmission Channel Characteristics
Total Length: 3 235,00 metres
Trapeze Type: 1 981,00 metres
Vertical Channel Type: 1 254,00 metres
Net Head: 23,86 metres
Penstock Pipe Diameter: 3 x 3500 mm
Regulator Type: 4 x Radial Gate, Concrete Weighted Power House
Hydraulic Turbines: 4 x Radial Gate, Concrete Weighted Power House
Power House Generators: : 3 x Vertical Axis Synchronous
Agreement Date: 06.11.2007
Taşyapi Energy
Agreement Date: 04/01/2008 - Work Completion Date: 30/04/2009
Yavuz Hydroelectric Power Plant
- ALL
- PHOTOS
- VIDEOS